Rough-Cut Capacity Calculator

Calculate rough-cut capacity by multiplying MPS quantities by hours per unit per work center. Validate master schedule feasibility quickly.

units
hrs
hrs
%
%
RCCP Load vs Capacity50.5%
Load: 258 hrsCapacity: 510 hrs
Gross Load (incl. scrap)
257.7 hrs
515 units ร— 0.5 hrs/unit
Net Load
250.0 hrs
500 good units ร— 0.5 hrs/unit
Scrap Allowance
7.7 hrs
3% scrap rate adds 15 units
Total Capacity
510.0 hrs
2 shift(s) ร— 300 hrs ร— 85% eff.
Capacity Gap
+252.3 hrs
Feasible โ€” surplus capacity
Load %
50.5%
Within safe operating range
Max Producible Units
1,020
At 0.5 hrs/unit with current capacity
Days to Complete
1.0 days
At effective capacity of 255 hrs/shift/day
Min. Shifts Needed
2
Current shift count is sufficient

Weekly Load Profile

WeekLoad (hrs)Capacity (hrs)UtilizationGapStatus
Week 151.5127.5
40%
+76.0OK
Week 277.3127.5
61%
+50.2OK
Week 377.3127.5
61%
+50.2OK
Week 451.5127.5
40%
+76.0OK

RCCP Feasibility Reference

Load RangeVerdictAction
0โ€“70%FeasibleMPS is achievable with room for variability
70โ€“90%TightFeasible but monitor for disruptions
90โ€“100%At RiskPrepare overtime or backup resources
>100%InfeasibleRevise MPS, add shifts, or outsource
Planning notes, formulas, and examples

About the Rough-Cut Capacity Calculator

Rough-Cut Capacity Planning (RCCP) is a quick validation that the Master Production Schedule is feasible from a capacity perspective. It multiplies planned production quantities by the standard hours required per unit at each key work center, then compares the total load against available capacity.

RCCP is intentionally simple โ€” it does not consider detailed scheduling or operation sequencing. Its purpose is to catch major capacity overloads before they cascade into detailed planning. If RCCP shows 140% loading at a work center for a given week, the MPS needs adjustment before running MRP.

This calculator performs RCCP for a single work center. Enter the MPS quantity, hours per unit at that work center, and available capacity to see the load percentage and any overload or available capacity gap.

Precise measurement of this value supports data-driven planning and helps manufacturing professionals make informed decisions about resource allocation and process optimization strategies. Quantifying this parameter enables systematic comparison across time periods, shifts, and production lines, revealing patterns that might otherwise go unnoticed in routine operations.

When This Page Helps

An infeasible MPS wastes everyone's time โ€” MRP generates orders that cannot be executed, purchasing orders materials that will arrive but cannot be processed, and the shop floor scrambles. RCCP catches problems early.

How to Use the Inputs

  1. Enter the MPS quantity for the period.
  2. Enter the standard hours per unit required at the work center.
  3. Enter the available capacity in hours at the work center for the same period.
  4. View the total load in hours and the load percentage.
  5. If load exceeds capacity, adjust MPS quantities or add capacity.
  6. Repeat for each critical work center.
Formula used
Load (hours) = MPS Qty ร— Hours per Unit Load % = (Load / Available Capacity) ร— 100 Overload/Underload = Load โˆ’ Available Capacity

Example Calculation

Result: 250 hrs load, 125% โ€” overloaded by 50 hrs

Load = 500 ร— 0.5 = 250 hours. Available capacity is 200 hours. Load percentage is 125%, meaning the work center is overloaded by 50 hours. The MPS must be adjusted or overtime/outsourcing planned.

Tips & Best Practices

  • Focus RCCP on bottleneck and critical work centers โ€” not every machine.
  • Use bill of labor (hours per unit per work center) for accurate load factors.
  • Run RCCP every time the MPS changes.
  • Present results visually as a bar chart: load vs. capacity by week and work center.
  • For mixed products, sum the loads from all MPS items at each work center.
  • RCCP is a screening tool โ€” follow up with detailed CRP for confirmed schedules.

RCCP Methods

Three common RCCP methods are: (1) Capacity Bills โ€” multiplies MPS by hours per unit, (2) Resource Profiles โ€” distributes the load across time periods based on lead time offsets, and (3) Overall Factors โ€” uses a single labor-hours-per-unit aggregate. Capacity Bills is the most widely used.

Visual RCCP Reporting

The most effective RCCP output is a bar chart showing load vs. capacity for each week at each key work center. Bars extending above the capacity line are immediate red flags. This visual format makes capacity problems obvious to planners and managers.

Integrating RCCP into S&OP

Sales and Operations Planning (S&OP) meetings should include RCCP validation. Before committing to sales plans, the operations team must confirm that the implied MPS is feasible. RCCP provides the data to make this confirmation or highlight conflicts.

Sources & Methodology

Last updated:

Frequently Asked Questions

  • RCCP is a quick, high-level check using MPS quantities and aggregate time standards. CRP is a detailed check using planned and released order routing data. RCCP is faster but less precise; CRP is slower but more accurate.